Project: MAIN PIPELINE AND DEIR SAMIT RESERVOIR

Role: General Contracting
Client: USAID
Location: Hebron - Palestine
Date: Completed December 2010
Size: 12.5 km / 2000 m³
Engineer: MWH
Cost: $4,220,806

Construction of an approximate 12.5km of Ø300mm and Ø200mm new main water transmission pipeline from Tarqumia to Beit Awwa. The pipeline will be connected to an existing Ø300mm water pipeline in Tarqumia. The works also include the construction of a new 2000m³ reinforced water reservoir in Deir Samit.